The following excerpt will be/is part of the “public comment presented” to the Coastal Commissison for their Hearing tomorrow. Fifty million dollars will buy a lot of bananas. It’s also strange that the CC says they’re interested in “cost,” but is that anything more than window-dressing and/or an optional consideration? And what about the goal of competitive bidding as promised in the 218 vote? More window-dressing? More options? And what’s with the reference to “change orders,” which, of course, equals a no-cap, open ended, sky’s the limit cost.
Well, anybody want to lay odds on how the votes as to how “cost” and fair-bids and change orders will fare Friday? Naw, me neither. Not here in “Chinatown,” at any rate. Done deals is done deals and if the community wants a more expensive project, then who is the Coastal Commission to deny them their wish?
Honorable Commissioners:
I am Dana Ripley, team leader for the Los Osos Wastewater Plan Update1
The process schematic of the 2006 Update Plan is very similar to the process schematic that I prepared for inclusion in the recently published “Water Reuse” textbook (McGraw Hill, 2007) as Figure 13-15. Thecaption of that figure reads:prepared in 2006 for the Los
Osos Community Services District.
Our final report was completed in August 2006 and was validated by the National Water Research Institute in December 2006. Septic Tank Effluent Pump (STEP) collection isfundamental to the “2006 Update Plan” and is, in my opinion, fundamental to the long term success ofthe Los Osos wastewater project.
Schematic flow diagram of comprehensive water reclamation and reuse plan incorporating STEPsystems for low-, medium-, and high-density communities.
A copy of this schematic is provided as Attachment A. It represents what I believe to be state-of-the-artin small community wastewater collection, treatment, and reuse whether constructed for a new development or for an existing community upgrading to central collection and treatment.
My testimony to the Commission today will focus on cost and affordability. CC staff recognizes the importance of affordability to Los Osos homeowners and businesses as follows:
The affordability of the project has been and will continue to be a major concern for the residents of Los Osos2
1 Ripley Pacific Company, Los Osos Wastewater Management Plan Update for the Los Osos Community ServicesDistrict, San Luis Obispo County, CA, Wastewater Collection Treatment, Storage, and Water Recycling: Beneficial Reuse of Water and Nutrients. Digital and hardcopy provided to CC-Santa Cruz staff on February 8, 2010..
2 Application A-3-SLO-09-055/069 staff report, May 27, 2010, p.2
The single largest factor influencing affordability is obviously the project’s construction cost. The estimated construction cost of the 2006 Update Plan prepared by our team is presented as AttachmentB3. For comparison, San Luis Obispo County’s latest cost estimate for the gravity-based system is presented as Attachment C4
Based on my review of the two construction cost budgets, assuming service to both developed and undeveloped properties and cost escalation to 2010 dollars, the cost difference between the two systems is at least $50 million. That is, the 2006 Ripley Update Plan cost utilizing STEP collection technology is at least $50 million less than the cost for the County’s gravity-based collection, treatment, and reuse plan..
The actual cost difference between the two system alternatives could in fact be substantially greater than $50 million. For STEP construction, there is relatively low construction cost risk since excavations are shallow and impacts of unforeseen conditions can be mitigated easily. For this reason, the STEP contractor has offered a guaranteed maximum price cost basis to SLO County.
For gravity construction, however, construction cost risk is significantly higher due to deeper excavations and difficulty of dealing with unforeseen conditions such as high groundwater and archeological sites. The contractor will be required to fuse-weld at least 12% of the collection system and more if high groundwater is encountered beyond that already mapped. SLO County would be compelled to accept change orders for these unforeseen conditions which in essence provides for an open-ended contract, irrespective of what the winning competitive bid cost number is. Of course, the extent of change order costs cannot be known until project construction is complete.
I also note that the County’s budget for Broderson leachfields does not include a redundant disposal option as recommended by the project hydrogeologist due to the uncertainty of winter dispersal capacity at that site5
Based on the foregoing comments, it would be likely that the completed cost difference between the two systems could be substantially greater than the $50 million difference represented by the two attached budgets.
The Broderson leachfield system is a $6.1 million line item that may need to bereplicated at one or more other undetermined locations to provide sufficient winter dispersal capacity. Even with the minimum $50 million cost difference, the Commission is faced with at least two issues inconsistent with the Coastal Act if the applicant’s gravity collection system is constructed.
First, Coastal Act Section 30604(g) states:
The Legislature finds and declares that it is important for the commission to encourage th eprotection of existing and the provision of new affordable housing opportunities for persons of low and moderate income in the coastal zone.
3 2006 Ripley Update Plan, Table ES-5.
4 San Luis Obispo County, from SWRCB Credit Review Checklist, April 23, 2010, Table 1.1.
5 Spencer Harris, hydrogeologist, San Luis Obispo Planning Commission, June 30, 2009; “You’d better have capacity somewhere else.”
3Los Osos Wastewater Project Dana Ripley, PE CA Coastal Comm. June 11, 2010 De Novo Hearing Public Comment
A cost difference of this magnitude has a direct impact on affordability. A lower project construction cost will lessen the impact to low- and moderate-income residents living within the coastal zone.
Secondly, Coastal Act Section 30120 defines treatment works6
. . any devices and systems used in the storage, treatment, recycling, and reclamation of
municipal sewage or industrial wastes of a liquid nature to implement section 1281 of this title, or necessary to recycle or reuse water at the most economical cost over the estimated life of the works. .
, as follows:
Consistency with this section of the Coastal Act would require that the most economical plan be implemented, irrespective of any technology preference by the project owner. The $50 million difference in the two estimates would likely preclude the gravity system as a viable alternative.
I am aware of the applicant’s technology preference against STEP collection for reasons such as green house gas emissions, soil disturbance numbers, nitrogen removal, on-lot easements, and on-lot pumping. I believe that each of these issues can be resolved in favor of STEP collection given the opportunity in an open forum. It also must be reiterated that the STEP collection alternative was CEQA certified as environmentally superior in 2001, was determined to be a viable collection alternative in the current project EIR, and was intended to compete with gravity collection through the bidding process pursuant to the Proposition 218 assessment vote in 2007. Finally, the Request for Qualifications prepared by SLO County in December 2008 presented both gravity collection and STEP collection as accepted alternatives for interested design-build teams bidding on the Los Osos wastewater project.
Only with elevation of the STEP team into the competitive bidding process with guaranteed maximum bids can the $50 million cost differential presented above be ascertained one way or the other. The Commission should seek the assurance that the competitive bid process promised by the Proposition 218 vote will be preserved and that consistency with Coastal Act Sections 30120 and 30604 is upheld.
Including this requirement as a permit condition today will not only assure Proposition 218 and Coastal Act consistency, but will assure that project timelines remain in place to “maximize the project’s eligibility to receive funding support that can offset local costs” as urged by SLO County and your staff. Thank you for your consideration of these cost and affordability issues, and I am available for questions.
/dr
6 Definition of treatment works as set forth in Federal Water Pollution Control Act per Coastal Act Section 30120.
Showing posts with label Coastal Act. Show all posts
Showing posts with label Coastal Act. Show all posts
Thursday, June 10, 2010
Monday, June 07, 2010
Tick, Tick, Tick. Running the clock out on Los Osos
The Coastal Commission will be hearing the Los Osos Sewer Project late on Friday, June 11th down in Marina del Rey. It’s the last item on the Agenda so there can be little or no discussion, just bang, bang, bang, No Time, Move Along, Nothing to See Here.
Over at the Rock is a nice little recap of How Things Get Done In This County. Once again, nothing to see here, move along, too late, Done Deal.
Actually, it was a Done Deal before the horse got out of the gate. Remember Noel King spilling the beans even before the TAC was formed? Oops. From there on, it was just a matter of a little grease there, a little spin here, orchestrated by Paavo and Gibson with a clueless/compliant Board (Move along, Boys, nothing to see here) and a clueless, manipulated community.
Well, that’s how it’s done in this county. And how it’s done when horses are put before carts; “Processes” are corrupted and deals are done. And, too bad for Los Osos. They’ll never know what the hard numbers would have been on an actual clean Design Build process and project. Guestimates, but no hard numbers.
Well, thanks to a spun “public survey,” the corruption of the Design Build “Process,” the lack of real numbers, threats and electioneering by the Water Board, the homeowners picked from a carefully selected and limited list of options, without protest, so now they’ll get what they said they wanted: gravity system, sewer plant out of town, water reuse, affordable/cheaper/cheapest.
Well, sort of. The last wish –“affordable”—was never really possible. There was always just “unaffordable,” “really unaffordable,” and “holy s*#t! unaffordable.” And since we never had a real Design Build process, we never had real numbers so “cheapest” remains an unreal and unreliable “guestimated” moving target that can be manipulated at will. Which means that come Saturday, the community will get three out of four wishes. They could have had four out of four, except that Paavo & Gibson, Inc, were in charge of the show from Day One, so the community will be getting what they are given.
And, to give the devil his/her due, thanks to Sarah Christie and the Planning Commission, they’ll be given a much better project than the sprayfield plan the county was trying to ram through, (an expensive attempted ram-through that wouldn’t have happened had we been allowed to stick to the original (promised) plan of a clean process and clean DP. Sprayfields wouldn’t have made the final cut.) So, I guess we should be grateful for small miracles.
Over at The Rock is posted a glimpse of this game. Read it and . . . laugh? http://rockofthecoast.com/news/local/868-ogrens-mwh-gravity-bias-costing-los-osos-tens-of-millions
Yep, that’s how it’s done.
Over at the Rock is a nice little recap of How Things Get Done In This County. Once again, nothing to see here, move along, too late, Done Deal.
Actually, it was a Done Deal before the horse got out of the gate. Remember Noel King spilling the beans even before the TAC was formed? Oops. From there on, it was just a matter of a little grease there, a little spin here, orchestrated by Paavo and Gibson with a clueless/compliant Board (Move along, Boys, nothing to see here) and a clueless, manipulated community.
Well, that’s how it’s done in this county. And how it’s done when horses are put before carts; “Processes” are corrupted and deals are done. And, too bad for Los Osos. They’ll never know what the hard numbers would have been on an actual clean Design Build process and project. Guestimates, but no hard numbers.
Well, thanks to a spun “public survey,” the corruption of the Design Build “Process,” the lack of real numbers, threats and electioneering by the Water Board, the homeowners picked from a carefully selected and limited list of options, without protest, so now they’ll get what they said they wanted: gravity system, sewer plant out of town, water reuse, affordable/cheaper/cheapest.
Well, sort of. The last wish –“affordable”—was never really possible. There was always just “unaffordable,” “really unaffordable,” and “holy s*#t! unaffordable.” And since we never had a real Design Build process, we never had real numbers so “cheapest” remains an unreal and unreliable “guestimated” moving target that can be manipulated at will. Which means that come Saturday, the community will get three out of four wishes. They could have had four out of four, except that Paavo & Gibson, Inc, were in charge of the show from Day One, so the community will be getting what they are given.
And, to give the devil his/her due, thanks to Sarah Christie and the Planning Commission, they’ll be given a much better project than the sprayfield plan the county was trying to ram through, (an expensive attempted ram-through that wouldn’t have happened had we been allowed to stick to the original (promised) plan of a clean process and clean DP. Sprayfields wouldn’t have made the final cut.) So, I guess we should be grateful for small miracles.
Over at The Rock is posted a glimpse of this game. Read it and . . . laugh? http://rockofthecoast.com/news/local/868-ogrens-mwh-gravity-bias-costing-los-osos-tens-of-millions
Yep, that’s how it’s done.
Friday, August 21, 2009
Call My Lawyer and Then Head For The Fences?
The following email was sent to me by Al Barrow/Los Osos Legal Defense Fund. Posted with permission.
Dear Coastal Commissioners:
SLO County promised in the 218 tax vote that funded the Los Osos Sewer project:
"In the current project selection strategy, the STEP and gravity alternatives would compete through the construction bidding phase using a competitive bid, design/build, and/or build/own/operate/transfer process. "
That was signed by the Assessment Engineer and PW Director Paavo Ogren.
But they have removed the lower impact collection system, which was adjudged in their two year fine screening process as a "viable alternative" out off the Design/Build project delivery method. Now only the most impactive project on coastal resources remains. Gravity deep trenching in liquefaction conditions is what the SLO County has chosen as their only project. A loss of 300,000 gpd of drinking water through leakage into the collection system. Gravity is many millions of dollars more cost, a cost that the lower income half of the population cannot afford, $3000.00 a year.or 8 times average cost.
In order to put STEP/STEG or vacuum collection, which are far more protective of coastal resources, we ask that you direct the SLO County to do so immediately. Something that the SLO Country planning commission did not do in their recent findings.
We also believe, in order to protect our community and environment, we must have legal counsel so we have engaged the Law offices of Jesse LB.Hill to see that the Local Coastal Plan, The Coastal Act and the supporting laws in the CZLUO are respected and that the environment is once again is not sacrificed.
We would hope that the SLO County would be sensitive to our concerns as we have submitted them, but that has not been the case in most issues of concern. As we prepare for the coming BOS and Coastal commission we ask all parties to reconsider the impact of removing a more protective and affordable collection technology.
Our position is that SLO County violated the 218 process by promising a Design/Build process that included STEP/STEG, then after the vote removing it, damaging the ratepayers with exorbitantly higher wastewater fees, charges and capital costs, when a more compliant technology is at lower costs and impacts that is also quicker to install.is already pre-designed in the LOCSD Ripley Report 2006.
SLO County admits there will be design changes required for their purportedly "shovel ready" collection system whose slopes are to shallow for solids to move through the collection pipes as the design flows are much lower than the original Montgomery Watson Harza design plans called for.
In order to avert "the train wreck" at the Coastal Commission Hearings we seek relief in the form of direction from your staff who have sent two directional letters to SLO County to date.
We also request by FOIA all communications whether phone memos, emails and letters relating to the LOWWP Coastal Development permit application.
Thank You,.Al Barrow
Los Osos Legal Defense Fund
P.O Box 6931
Los Osos CA 93412 805 534-0800 Thank you for your support.
Dear Coastal Commissioners:
SLO County promised in the 218 tax vote that funded the Los Osos Sewer project:
"In the current project selection strategy, the STEP and gravity alternatives would compete through the construction bidding phase using a competitive bid, design/build, and/or build/own/operate/transfer process. "
That was signed by the Assessment Engineer and PW Director Paavo Ogren.
But they have removed the lower impact collection system, which was adjudged in their two year fine screening process as a "viable alternative" out off the Design/Build project delivery method. Now only the most impactive project on coastal resources remains. Gravity deep trenching in liquefaction conditions is what the SLO County has chosen as their only project. A loss of 300,000 gpd of drinking water through leakage into the collection system. Gravity is many millions of dollars more cost, a cost that the lower income half of the population cannot afford, $3000.00 a year.or 8 times average cost.
In order to put STEP/STEG or vacuum collection, which are far more protective of coastal resources, we ask that you direct the SLO County to do so immediately. Something that the SLO Country planning commission did not do in their recent findings.
We also believe, in order to protect our community and environment, we must have legal counsel so we have engaged the Law offices of Jesse LB.Hill to see that the Local Coastal Plan, The Coastal Act and the supporting laws in the CZLUO are respected and that the environment is once again is not sacrificed.
We would hope that the SLO County would be sensitive to our concerns as we have submitted them, but that has not been the case in most issues of concern. As we prepare for the coming BOS and Coastal commission we ask all parties to reconsider the impact of removing a more protective and affordable collection technology.
Our position is that SLO County violated the 218 process by promising a Design/Build process that included STEP/STEG, then after the vote removing it, damaging the ratepayers with exorbitantly higher wastewater fees, charges and capital costs, when a more compliant technology is at lower costs and impacts that is also quicker to install.is already pre-designed in the LOCSD Ripley Report 2006.
SLO County admits there will be design changes required for their purportedly "shovel ready" collection system whose slopes are to shallow for solids to move through the collection pipes as the design flows are much lower than the original Montgomery Watson Harza design plans called for.
In order to avert "the train wreck" at the Coastal Commission Hearings we seek relief in the form of direction from your staff who have sent two directional letters to SLO County to date.
We also request by FOIA all communications whether phone memos, emails and letters relating to the LOWWP Coastal Development permit application.
Thank You,.Al Barrow
Los Osos Legal Defense Fund
P.O Box 6931
Los Osos CA 93412 805 534-0800 Thank you for your support.